Recent Recommendation Status Updates

Each recommendation the CSB issues is monitored by CSB staff from the time it is issued to closing. CSB staff evaluate recipient responses, and the Board votes to assign status designations to recommendations based on staff evaluation. This page highlights recommendations for which the Board has recently voted to change the status of the recommendation. For more information on how the CSB defines its recommendation statuses, please visit the Recommendations Frequently Asked Questions page.

To contact CSB Recommendations Staff please email recommendations@csb.gov 

 

Expand All

Recommendations

Oil Tank Safety Study (1 Recommendations)
State of Oklahoma/Oklahoma Corporation Commission (1 Recommendations)
Open: 100% | Closed: 0%

Final Report Released On: October 27, 2011

2011-H-1-3

Amend state oil and gas regulations to:

a) Protect storage tanks at exploration and production sites from public access by requiring sufficient security measures, such as full fencing with a locked gate, hatch locks on tank manways, and barriers securely attached to tank external ladders and stairways.

b) Require hazards signs or placards on or near tanks that identify the fire and explosion hazards using words and symbols recognizable by the general public.

c) Require the use of inherently safer tank design features such as flame arrestors, pressure vacuum vents, floating roofs, vapor recovery systems or an equivalent alternative, to prevent the ignition of a flammable atmosphere inside the tank.


Status: Open - Acceptable Response or Alternate Response
Open - Acceptable Response or Alternate Response (O - ARAR) - Response from recipient indicates a planned action that would satisfy the objective of the recommendation when implemented.
 

PDF Document Recommendation Status Change Summary

Philadelphia Energy Solutions (PES) Refinery Fire and Explosions (1 Recommendations)
American Society for Testing and Materials (ASTM) International (1 Recommendations)
Open: 0% | Closed: 100%

Final Report Released On: October 11, 2022

2019-04-I-PA-5

Revise ASTM A234 to incorporate supplementary requirements for piping used in HF service, as defined in HF supplementary requirements S9.1 through S9.7 in ASTM A106 version 19a.


Status: Closed - Reconsidered/Superseded
Closed - Reconsidered/Superseded (C - R/S) - Recipient rejects the recommendation and also supports the rejection with a rationale with which the Board concurs. This designation may apply when later facts indicate that the concerns expressed in the recommendation were actually addressed prior to the incident, or when a recommendation is superseded by a new, more appropriate recommendation.
 

PDF Document Recommendation Status Change Summary

Arkema Inc. Chemical Plant Fire (1 Recommendations)
Arkema Crosby Facility (1 Recommendations)
Open: 0% | Closed: 100%

Final Report Released On: May 24, 2018

2017-08-I-TX-1

Reduce flood risk to as low as reasonably practicable (ALARP). Ensure that any safeguards for flooding meet independent layer of protection requirements.


Status: Closed - Acceptable Action
Closed - Acceptable Action (C - AA) - The recipient has completed action on the recommendation. The action taken meets the objectives envisioned by the Board.
 

PDF Document Recommendation Status Change Summary

Loy Lange Box Company Pressure Vessel Explosion (1 Recommendations)
Arise, Inc (1 Recommendations)
Open: 0% | Closed: 100%

Final Report Released On: July 29, 2022

2017-04-I-MO-7

Update company policies and/or procedures by including prescriptive elements in the boiler and pressure vessel repair and alteration inspection and acceptance process that would prevent the acceptance of a non-conforming repair or alteration.


Status: Closed - Acceptable Action
Closed - Acceptable Action (C - AA) - The recipient has completed action on the recommendation. The action taken meets the objectives envisioned by the Board.
 

PDF Document Recommendation Status Change Summary

Husky Energy Superior Refinery Explosion and Fire (16 Recommendations)
American Petroleum Institute (API) (3 Recommendations)
Open: 100% | Closed: 0%

Final Report Released On: December 23, 2022

2018-02-I-WI-13

Using API’s processes to determine the appropriate safety product, develop a publicly available technical publication for the safe operation of fluid catalytic cracking (FCC) units. The document should be applicable to both new and existing units. Include the following topics at a minimum:

a) Description of typical FCC unit hazards, including air leaks into hydrocarbon systems or hydrocarbon leaks into air systems that could form a flammable mixture during transient operation (startup, shutdown, standby, and the actions required to transition between these modes). If needed, include differences between possible reactor/regenerator configurations;

b) Recommended practices for safeguards to control FCC unit hazards;

c) Recommended monitoring for process safety during FCC unit transient operations;

d) Recommended emergency operating procedures for FCC-specific scenarios;

e) PHA guidance for key FCC-specific scenarios, including transient operation;

f) Recommended FCC-specific field and board operator process safety training topics and methods;

g) Guidelines for process safety assessments of FCC units; and

h) Incorporate lessons learned from this CSB investigation and the CSB’s ExxonMobil Torrance Refinery Electrostatic Precipitator Explosion investigation throughout the document and include references in the document’s bibliography.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-14

Modify the appropriate existing recommended practice (for example, API RP 553, Refinery Valves and Accessories for Control and Safety Instrumented Systems) to include information about the purpose, design, maintenance, and testing of additional FCC catalyst slide valve components, including the slide valve body. If an API product other than API RP 553 is modified, API RP 553 should guide the reader to that reference.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-15

Incorporate lessons learned from the FCC Unit Explosion and Asphalt Fire at Husky Superior Refinery incident into the appropriate API products (for example, API RP 2023, Guide for Safe Storage and Handling of Heated Petroleum-Derived Asphalt Products and Crude Oil Residua, or API RP 2021, Management of Atmospheric Storage Tank Fires). At a minimum, topics shall include the flammability of heated material such as asphalt and the ignition risk of pyrophoric material inside asphalt storage tanks. Include a reference to this CSB investigation in the document’s bibliography.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

Cenovus Energy, Inc. (3 Recommendations)
Open: 100% | Closed: 0%

Final Report Released On: December 23, 2022

2018-02-I-WI-8

For all Cenovus operated refineries with FCC units, develop and implement an FCC unit-specific PHA guidance document as part of each FCC unit’s ongoing PHA update/revalidation cycle, including the Cenovus Superior Refinery. The PHA guidance document should be updated with new industry knowledge as it becomes available (for example, from AFPM, CCPS, and API). The PHA guidance document should include a requirement to review available licensor and industry guidance for FCC unit PHA scenarios and recommended safeguards and at a minimum, include information related to transient operation safeguards listed in CSB Recommendation 2018-02-I-WI-R1.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-9

Develop and implement a technology-specific knowledge-sharing network program across all Cenovus operated refineries, which at a minimum includes an FCC technology peer network. The peer network(s) must include engineers, operations management, and operations staff from each site that uses the technology, including the Cenovus Superior Refinery. The network(s) must meet at least annually to discuss process safety topics in the technology including:

a) Relevant incidents and near-misses at the refineries and/or in industry;
b) Refinery learnings in implementing process safety improvements;
c) Relevant industry tools, bulletins, and knowledge-sharing documents, such as those published by AFPM, CCPS, and API; and
d) Relevant updates to industry publications and standards.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-10

Include and maintain the FCC technology licensors’ operating manuals in the process safety information packages for all FCC units, including the FCC unit at Cenovus Superior Refinery.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

Cenovus Superior Refinery (7 Recommendations)
Open: 100% | Closed: 0%

Final Report Released On: December 23, 2022

2018-02-I-WI-1

Establish safeguards to prevent explosions in the FCC unit during transient operation (including startup, shutdown, standby, and emergency procedures). Incorporate these safeguards into written operating procedures. At a minimum establish the following specific safeguards:

a) Implementation of the reactor steam barrier, or a similar inert gas flow, to maintain an inert barrier at an elevated pressure between the main column (containing hydrocarbon) and the regenerator (containing air);

b) Purging the main column with a non-condensable gas as needed to prevent a dangerous accumulation of oxygen in the main column overhead receiver;

c) Monitoring to ensure that there is a sufficient non-condensable gas purge of the main column to prevent a dangerous accumulation of oxygen in the main column overhead receiver (either through direct measurement of the oxygen concentration and/or through engineering calculation);

d) Monitoring of critical operating parameters for flows, pressures, pressure differences, and catalyst levels;

e) Documentation of consequences of deviating from the transient operation safe operating limits and of predetermined corrective actions; and

f) Inclusion of the above items in the appropriate FCC operator training curricula.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-2

Based on licensor input and good industry practices, determine the appropriate point(s) in the FCC unit’s shutdown procedures to shut down all wet gas compressor(s). Incorporate this information into all FCC unit shutdown procedures and operator training material.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-3

Develop and implement a slide valve mechanical integrity program that addresses erosion and ensures proper functioning of the slide valves during a shutdown. The program must include, at a minimum:

a) A slide valve mechanical integrity standard that defines monitoring and inspection requirements, with acceptance criteria, required for the safe operation of the FCC unit during transient operation (such as a startup, shutdown, standby, and emergency).

b) Monitoring that includes process data analysis and mechanical preventive activities to evaluate the mechanical condition of the slide valves during the operation of the FCC unit between turnarounds;

c) Quarterly presentations of process data and mechanical preventive maintenance data to refinery operations management and maintenance management to drive key decisions such as shortening the turnaround cycle and/or planning a maintenance outage;

d) During turnarounds and other potential slide valve maintenance outages, evaluate the adequacy of the slide valve mechanical integrity program for the safe operation of the FCC unit during transient operation. If the inspection demonstrates unsuccessful performance, make appropriate corrections.

During the next major FCC unit turnaround at Cenovus Superior Refinery, demonstrate that the slide valve mechanical program is adequate for the safe operation of the FCC unit during transient operation. If the inspection demonstrates unsuccessful performance, make appropriate corrections to the slide valve mechanical integrity program.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-4

Develop emergency procedures for responding to a loss of catalyst slide valve function (for example, when it leaks excessively or fails to close on demand).


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-5

Develop guidance for analyzing operating procedures to improve transient operation hazard evaluations during PHAs. Refer to section Chapter 9.1 in the CCPS publication Guidelines for Hazard Evaluation Procedures, 3rd Ed. or an appropriate equivalent resource to develop the guidance. Incorporate the guidance into the appropriate Cenovus Superior Refinery PHA procedural documents and policies.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-6

Develop and implement an FCC unit operator, supervisor, and manager training program based on the licensor’s guidance and on available industry guidance. Elements of the training program shall include:

a) A set of written training materials (such as a manual) consistent with the licensor’s technology information, encompassing:

i) FCC equipment;
ii) Normal operations;
iii) Transient operations (including startup, shutdown, standby, and emergency); and
iv) Case studies of industry FCC industry incidents, including ExxonMobil Torrance (2015) and this incident; and

b) Training delivery methods including:

i) Group and individual training; and
ii) Simulator training for board operators.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

2018-02-I-WI-7

Incorporate lessons learned from this incident into the appropriate training materials for the Cenovus Superior Refinery Emergency Response Team. At a minimum, topics shall include the proper response to liquids potentially stored above their flash point, such as asphalt, and the ignition risk of pyrophoric material inside asphalt storage tanks.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

Environmental Protection Agency (EPA) (1 Recommendations)
Open: 100% | Closed: 0%

Final Report Released On: December 23, 2022

2018-02-I-WI-12

Develop a program that prioritizes and emphasizes inspections of FCC units in refineries that operate HF alkylation units (for example, under EPA’s National Compliance Initiative called Reducing Risks of Accidental Releases at Industrial and Chemical Facilities). As part of this program, verify FCC unit safeguards that prevent explosions during transient operation (including startup, shutdown, standby, and emergency procedures). At a minimum the program will verify the following specific safeguards:

a) Implementation of the reactor steam barrier, or a similar inert gas flow, to maintain an inert barrier at an elevated pressure between the main column (containing hydrocarbon) and the regenerator (containing air);

b) Purging the main column with a non-condensable gas as needed to prevent a dangerous accumulation of oxygen in the main column overhead receiver;

c) Monitoring to ensure that there is a sufficient non-condensable gas purge of the main column to prevent a dangerous accumulation of oxygen in the main column overhead receiver (either through direct measurement of the oxygen concentration and/or through engineering calculation);

d) Monitoring of critical operating parameters for flows, pressures, pressure differences, and catalyst levels;

e) Documentation of consequences of deviating from the transient operation safe operating parameters and of predetermined corrective actions; and

f) Inclusion of the above items in the appropriate FCC operator training curricula.

This recommendation is in addition to the recommendations to EPA relating to hydrofluoric acid outlined in the CSB’s report on the 2019 fire and explosions at the Philadelphia Energy Solutions refinery. In that report, the CSB recommended (1) that the EPA prioritize inspections of refinery HF alkylation units to ensure units are complying with API good practice guidance, (2) to require petroleum refineries with HF alkylation units to evaluate inherently safer technology, and (3) to initiate prioritization and, as applicable, risk evaluation of HF under the Toxic Substances Control Act.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

Honeywell UOP (Universal Oil Products) (1 Recommendations)
Open: 100% | Closed: 0%

Final Report Released On: December 23, 2022

2018-02-I-WI-16

Participate in the API committee that develops a technical publication for the safe operation of FCC units.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary

Occupational Safety and Health Administration (OSHA) (1 Recommendations)
Open: 100% | Closed: 0%

Final Report Released On: December 23, 2022

2018-02-I-WI-11

Develop guidance documents for performing process hazard analysis on operating procedures to address transient operation hazards in facilities with Process Safety Management (PSM) covered processes.


Status: Open - Awaiting Response or Evaluation/Approval of Response
Open - Awaiting Response or Evaluation/Approval of Response (O - ARE/AR) - The recipient has not submitted a substantive response, or the evaluation by CSB staff of a response is pending, or the Board has not yet acted on staff recommendation of status.
 

PDF Document Recommendation Status Change Summary